Commercial Solar Installation in Auburn, NSW

AYKA Solar designed and installed a 96.250kW solar power system for a commercial property in Auburn, NSW. The system comprises 175 JA Solar 550Wp panels paired with Solis 50kW and 30kW inverters, generating approximately 140,500 kWh/year.

Project Overview

AYKA Solar implemented a robust 96.250 kWp on-grid solar system, showcasing our capability to handle large-scale commercial solar projects efficiently.

System Specifications

  • Project Size: 96.250 kWp
  • System Type: On-Grid System
  • Panel Type: 175qty x JA Solar 550Wp (JAM72S30-550/GR/1500V)
  • Inverter Type: 1 x SOLIS – Ningbo Ginlong Technologies 50kW (S5-GC50K), 1 x SOLIS – Ningbo Ginlong Technologies 30kW (S5-GC30K-AU)
  • Racking System: Titan Solar or Grace Racking System (as per Australian Standards)
  • Annual Energy Generation: Approx. 1.4 MWh/year

Challenges and Solutions

Limited Roof Space Utilization

Challenge: The roof design and space constraints required precise planning to achieve maximum energy output.

Solution:

Conducted a detailed site survey to analyze space availability and sunlight exposure.

Used efficient JA Solar 550Wp panels, which deliver high energy output even with limited space.

Optimized panel arrangement to ensure minimal shading and maximum power generation.

 Client Concern for Long-Term Reliability

Challenge: The client needed assurance of the system’s durability and efficiency over its lifetime.

Solution:

Recommended JA Solar panels, known for their industry-leading efficiency and longevity.

Installed Solis inverters, which offer superior reliability, easy monitoring, and advanced grid compatibility.

Energy Load Management

Challenge: Ensuring the system could handle the facility’s varying energy demands efficiently.

Solution:

Designed a dual inverter system combining 50kW and 30kW Solis inverters to manage energy loads dynamically.

Configured the system to optimize energy use and minimize reliance on the grid during peak hours.

Compliance and Installation Timeline

Challenge: Meeting tight deadlines while adhering to strict compliance requirements for commercial solar installations.

Solution:

Handled all regulatory approvals and grid connection applications in line with CEC standards.

Deployed AYKA Solar’s experienced team to complete the project on schedule without compromising quality.

Results

  • Annual Energy Generation: 140,500 kWh/year
  • Electricity Cost Reduction: Up to 75% annual savings on energy bills.
  • Environmental Impact: Offset of approximately 115 metric tons of CO₂ emissions per year.
  • Increased Property Value: The solar installation enhanced the facility’s market value as a sustainable asset.

Conclusion

Despite initial challenges, AYKA Solar successfully delivered a reliable and efficient solar power system tailored to the client’s needs. By adopting advanced technology and smart design, the client now enjoys significant cost savings and contributes to a sustainable future.

Scale your business sustainably. Contact AYKA Solar to explore how our large-scale solar solutions can power your enterprise efficiently and sustainably.

Your Trusted Partner in Commercial Solar

AYKA Solar specializes in providing innovative, high-performance solar solutions for businesses in Luddenham, NSW, and surrounding areas. With proven success, we ensure every system delivers unmatched reliability and value, helping businesses grow sustainably and profitably.

Want a similar solution for your property?

Send A Message

other project examples

Austpath Laboratories, Northmead, NSW – 100kW

Efficient and reliable system installed at AUSTPATH LABORATORIES. 263 top quality REC 380W panels with German made SMA inverters.

Church, Thornleigh, NSW – 25kW

25kW system with reliable LONGI panels and European made FRONIUS inverter make a powerful combination in solar power plant.

Fruit World, Luddenham, NSW – 40kW

A massive 40kW system with reliable Trina panels and a powerful 29.9kW Huawei inverter for Fruit World.

Swimming center, Hornsby, NSW – 38.7kW

Commercial solar installation of 38.7kW system for a client in Hornsby. A powerful combination of Longi Half cut mono crystalline 450W panels and 29.9kW Huawei inverter.

Commercial Installation – 22.2kW

A 22.2kW system was installed using a combination of an Austrian made Fronius inverter and Trina 370W Half cell monocrystalline panels in solar power plant.

Supreme Engineering, Blacktown, NSW – 20kW

Our friends from Supreme Engineering are enjoying their new 20KW solar panel system – A powerful and efficient system with combination of Longi panels and Fronius inverter.

Refer & Earn Up to $2,000* Just by Helping a Business to Go Solar

T&C Apply*

Get Rewarded for Every Referral

ayka solar

Your Trusted solar installer

At Ayka, we’re proud to be leading Australia’s solar charge. Helping smart Aussies make a real difference to the planet, reducing their reliance on the grid, cutting their energy bills, and connecting them to their smart energy future.

Since 8 years, we’ve been the trusted name in Australian solar, installing over a million solar hot water systems in over 70 countries, and over 700,000 solar power panels in Australia.

AYKA SOLAR SOLUTION AUSTRALIA

most satiesfied customers solar installers

×
Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.